Skip to content
City PM
  • Germany
  • France
  • Europe
  • Markets
  • Business
  • Opinion
  • Germany
  • France
  • Europe
  • Markets
  • Business
  • Opinion
Wednesday 08 March 2023 7:12 pm  |  Updated:  Friday 14 April 2023 9:49 am

National Grid is the biggest roadblock to reviving onshore wind, argues Octopus

By: Nicholas Earl

Add as a preferred source on Google

The biggest challenge for onshore wind developments is the same as for all renewable projects – the slow speed of connections on the grid, the boss of a leading renewables player has argued.

Zoisa North-Bond, chief executive of Octopus Renewables, criticised the grid as the “biggest limiting factor” rather than planning hurdles and nimbyism.

The energy boss noted that with offshore wind projects, it was taking up to a decade to connect turbines to the energy network – this was a challenge that would be replicated onshore with new turbines as well.

She argued that the processes of National Grid – the company that oversees the UK’s energy networks – were obsolete for the challenge of vastly ramping up renewable power in line with energy security and net zero goals.

“When you look at the processes that they are using for all of this distributed, wonderful generation that we’re bringing in – it’s still based on ones from decades ago, where you connect the single coal fired power station and maybe there’ll be two or three applications every few years,” North-Bond explained.

This contrasted sharply with the current situation in the energy sector, where National Grid is having to process thousands of applications every year for new starter projects.

She also argued developments could be helped if National Grid could provide more data to applicants for new projects on which areas of the country had the best capacity to connect new projects.

“When you’re putting your application together, very often it’s a yes or no decision and it can be quite a negative experience,” she explained, “but if the grid could actually get much better at showing areas of the country where you have capacity to connect projects, then you can apply a very ‘can-do’ attitude to the way that you developed into the future.”

When approached for comment, a National Grid spokesperson said: “We’re committed to connecting projects to the grid as fast as possible. A majority of projects in the pipeline have connection dates within 12 months of their requested date, and we’re working with the electricity system operator, Ofgem, and wider industry to introduce new ways to speed up the process for others.

“As well as refining the connections pipeline, we’re collaborating with industry to push for policy and regulatory reform to allow us to make earlier decisions on longer term planning and network investment, supporting faster progress towards a clean and affordable energy system.”

Only 13GW of offshore wind have been fully commissioned – a situation that could await onshore wind (Source: Renewable UK)

We will speed up the process, says National Grid

National Grid has set up a temporary amnesty to deal with criticisms of its approval pipeline for new projects – providing companies the ability for people to exit the queue if they feel the development is not going to go ahead, without having to suffer financial penalties.

As things stand, proposed new renewable energy projects enter the Transmissions Entry Capacity queue, which are approved on a first come first serve basis, rather than whether they are fully funded and ready to go.

It also faces a vast infrastructure challenge, with National Grid pledging £40bn investment in critical infrastructure over the next four years, raising its commitments from previous expectations of £30-35bn.

This includes £29bn targeted towards decarbonising energy networks across the country.

Chief executive John Pettigrew confirmed to the BBC last year that National Grid will have to build around seven times as much infrastructure over the current decade as it has constructed in the past 32 years to meet the country’s renewable energy goals.

However, North Bond’s perspective was shared by the National Infrastructure Commission, which urged for a bolder approach in building projects to reach net zero.

The commission’s chair, Sir John Armitt, said: “The last 18 months has underlined the many reasons to unleash the full benefits of renewable generated electricity. The operators who literally have the power to help us achieve the green transition need an efficient system for getting connections and a grid behind it that is ready for them.

Read more

Upgrading the grid risks ending up like HS2

Electricity grid infrastructure with high-voltage power lines and pylons under a clear sky, representing energy distribution.

“We must go further, faster to break up the logjams standing in the way of getting them connected, and getting the UK onto cheaper, more secure power supply for the long term.”

Wind is becoming an increasingly significant factor in the UK’s energy mix (Source: grid.iamkate.com)

Meanwhile, Adam Berman, deputy director of trade association Energy UK, was also concerned about developing infrastructure in line with demand – but argued Ofgem and the government would need to reform the rules National Grid enforces.

He said: “Achieving a decarbonised power system will require that we rapidly expand the UK’s grid. It’s important to be realistic that – were the ban on onshore wind to be lifted – it would take some time for projects to move through the permitting and construction stages.

“This would allow new network infrastructure to be built. This will be significantly quickened if the government and Ofgem think seriously at how to make it easier to build grid, for example through allowing networks to put in place anticipatory investment that can bring down the overall project timeline.”

When approached for comment, an Ofgem spokesperson said:“Ofgem is working at pace to deliver the regulatory framework needed to achieve the government’s net zero ambitions, which will require a far more flexible and dynamic energy system. 

“We’re also working with government and the industry on ways to speed up new connections including reviewing the way networks manage connection queues. This should help improve the connection times for those wanting to connect to the electricity network.”

The government has been approached for comment.

Communities deserve a say in wind projects

While North-Bond was highly critical of the National Grid’s approach, she was more sympathetic to the government’s National Policy Planning Framework, which will define the planning rules for new developments nationwide including onshore wind.

It has recently included a consultation for onshore wind, where industry body Renewable UK warned it was “highly concerned” that the government is not doing enough to remove “the barriers preventing onshore wind from being rapidly deployed”.

Renewable UK has called for planning footnotes for onshore wind around local consent to be scrapped, bringing the energy source in line with other building projects.

However, North-Bond argued this was only a viable approach “ if we were wanting wind everywhere”.

Compare and contrast: the original planning footnote (below) with government’s proposed changes in purple (above)

She said: “We’ve seen that not all communities would accept wind turbines, and we have to actually focus on where people want these building. What the government has actually proposed is allowing the decision around developing wind turbines to remain at local level with local people.

“It’s actually going back to neighbourhood plans, local development plans, local authority plans, which we think is absolutely right. It should remain the community’s decision.”

Octopus Renewables has 300MW of onshore assets in the UK alongside offshore wind projects off the coast of Lincolnshire.

Renewable UK reported last month that just two onshore wind turbines were installed in England last year, as the industry awaits pledged planning reforms for new projects.

Overall, just ten new onshore wind projects were installed in 2022 across the UK, according to new research published by trade body Renewable UK.

Read more

AI data centre race reaches rural Devon as Xlinks eyes £3.6bn campus

Sir Keir Starmer's government has prioritised investment data centres as a major pillar of its plans to boost economic growth.

Share this article

  • Facebook
  • X
  • LinkedIn
  • WhatsApp
  • Email

Similarly tagged content:

Sections

  • News

Categories

  • Energy

Related Topics

  • Energy
  • Green energy
  • Octopus Energy
  • renewable energy

Trending Articles

  • Burnham tax plans spark investor rush to bank capital gains

  • Brewdog chief executive quits after only one year

  • Nothing fails to file accounts months after dissolution threat

  • UK ‘no longer a serious place’ says Hedge fund boss after losing £200m tax battle

  • Cruyff turn: Starmer allows pubs to stay open for England World Cup game

More from City PM

  • Upgrading the grid risks ending up like HS2

    Opinion
    Electricity grid infrastructure with high-voltage power lines and pylons under a clear sky, representing energy distribution.
  • AI data centre race reaches rural Devon as Xlinks eyes £3.6bn campus

    Tech
    Sir Keir Starmer's government has prioritised investment data centres as a major pillar of its plans to boost economic growth.
  • Here’s what a government led by Andy Burnham will look like

    Opinion
    Burnham cityscape featuring historic architecture and bustling streets under clear skies, highlighting urban development.
  • Thames Water, energy grid, rent prices: Burnham drums up public control agenda

    Politics
    Burnham skyline at sunset highlighting modern architecture against a vibrant orange and pink sky, reflecting urban develop...
  • Fuse boss attacks planning rules as a ‘self-imposed bottleneck for growth’

    Energy
    UK industrial electricity prices are the highest in the G7 and 46 per cent above the average of the International Energy Agency.
  • Carbon markets must industrialise or the net zero transition stalls

    Partner
    Close-up of a sapling at Aranya Reforestation site in India, showcasing efforts in sustainable forestry and ecological res...
  • Markets would take Miliband chancellor appointment ‘worse’ than Streeting, predicts Cavendish chief

    Markets
    Skyline of Canada with iconic financial district buildings, highlighting UK investments and economic growth.
  • Kraken Launches Autonomous Agents for Utility Customer Service Built in Partnership with Sierra

    Business Wire

City PM — European politics, business and analysis.

Europe

  • Germany
  • France
  • Europe
  • UK & Ireland

Topics

  • Business
  • Markets
  • AI
  • Technology
  • Opinion
  • Energy

More

  • Politics
  • Economics
  • Fintech
  • Legal
  • Sport
  • Life

Company

  • About City PM
  • Editorial Policy
  • Corrections
  • Contact
  • Terms of Use
  • Privacy Policy
  • Cookie Policy
© 2026 City PM · Published by CityPM Media, Bahnhofstrasse 65, 8001 Zürich, Switzerland
About · Editorial Policy · Corrections · Contact · Privacy