Lower Thames Crossing boss: HS2 debacle has driven investors and talent away from UK

By: Guy Taylor

Transport Reporter

Add as a preferred source on Google
Lower Thames Crossing northern tunnel entrance
Lower Thames Crossing northern tunnel entrance

Struggles at the embattled High Speed Two line are impacting the UK’s major infrastructure projects and driving some experts overseas, the man leading the delivery of Britain’s largest road tunnel has said.

Plans for the Lower Thames Crossing (LTC) involve building a new 14-mile road and tunnel east of London, linking Kent and Essex.

The £10bn project, one of the biggest in the UK, aims to relieve pressure on the busy Dartford Crossing, freeing up the M25 and improving journeys to and from the Port of Dover.

Matt Palmer, an industry veteran who has worked on Heathrow’s Terminal five and famous third runway proposals, told City PM the “biggest impact on LTC and elsewhere is industry morale.”

More secure pipelines, investment and infrastructure systems in other countries such as Saudi Arabia and Canada are now attracting experts overseas, he explained.

Palmer said he had already “lost a lead to Toronto, one of my my tunnel directors has left to go to build a tunnel in Canada. Now, is that directly responsible? He says well I don’t know what’s going on in the UK… safer bet elsewhere, and so we see a brain drain as a result of it.”

The northern leg of HS2 was axed in October amid balooning costs and ongoing delays, while the Euston section connecting the line to Central London is also facing setbacks. The project’s total budget could now reach more than £100bn, up from an initial £33bn.

The government and HS2 Limited has faced fierce political backlash over its handling of the high speed line’s delivery. While inflation has bumped up costs, the project’s business case and decisions including building much of the route in an underground tunnel have been questioned.

Read more

Why can the Faroe Islands build faster than Britain?

Underwater roundabout in the Eysturoy Tunnel, featuring modern engineering and design, credit Getty Images

One of my my tunnel directors has left to go to build a bloody tunnel in Canada. Now, is HS2 directly responsible? He says, well, I don’t know what’s going on in the UK

“I’ve never known the construction industry in the UK be quite so downbeat about itself, because actually, yes, there’s lots of bad things about HS2, but there’s some really good stuff as well and nobody’s willing to hear that story,” Palmer said.

“Imagine you’ve got I don’t know how many 1000s of people… probably 50 per cent of the construction sector is working on HS2 at the moment and as a country, we’ve just turned our back on it. So yeah as a construction it’s pretty depressing.”

It’s not just HS2. The UK’s infrastructure system is increasingly coming under fire for its excessive planning red tape and long delays, with many projects taking years to get off the ground.

Struggles at HS2 are affecting other UK major infrastructure projects, the man leading the delivery of the UK's largest road tunnel has said.
Matt Palmer. Struggles at HS2 are affecting other UK major infrastructure projects, the man leading the delivery of the UK’s largest road tunnel has said.

The planning application for the Lower Thames Crossing is the UK’s longest ever, at a whopping 359,000 pages and costing £267m prior to spades reaching the ground.

Even Crossrail, the railway construction project responsible for delivering the much-lauded Elizabeth Line, finished £3bn over budget after 20 years of planning.

“It makes Treasury and Central Government very nervous the experience they’ve had, and they would cite it as a sort of Crossrail, followed by HS2. So they’re worried by the historical problems of big programs and you know, it does lead you to… is government set up to do mega projects? You know, that is a good question.”

A Government spokesperson said: “We are removing barriers to investment by speeding up planning approvals, reducing the time it takes for new projects to connect to the grid and we have set out our 10 year forward look of major projects to help build confidence in future investment”.

A spokesperson for HS2 Ltd said: “We’ve been clear about our cost challenges, which have been compounded by significant levels of inflation. HS2 Ltd is now under new leadership and implementing changes across the programme aimed at controlling costs and learning the lessons of the past.”

Read more

Thames Water is Burnham’s first big test: will he do what’s right or what’s popular?

Thames Water infrastructure with pipes and valves, highlighting water management in urban areas amidst ongoing utility dis...

Share this article

  • Facebook
  • X
  • LinkedIn
  • WhatsApp
  • Email

Similarly tagged content:

Sections

  • News

Categories

  • Business
  • Transport & Infrastructure

Trending Articles

  • Citroën 2CV returns as a £13,000 electric car, and the timing is no accident

  • The former African gold miner taking on the billionaire Issa brothers

  • Exclusive: Big Four giant KPMG to cut more jobs

  • As it happened: Choppy day for FTSE 100 after Iran closes Strait of Hormuz as strikes ramp up

  • I was on the Goodyear blimp above London – here’s what it was like

More from City PM

  • Why can the Faroe Islands build faster than Britain?

    Opinion
    Underwater roundabout in the Eysturoy Tunnel, featuring modern engineering and design, credit Getty Images
  • Thames Water is Burnham’s first big test: will he do what’s right or what’s popular?

    Opinion
    Thames Water infrastructure with pipes and valves, highlighting water management in urban areas amidst ongoing utility dis...
  •  Thames Water eyes return to London Stock Exchange while Pennon back in profit

    Water
    Thames Water creditors have made a last-ditch offer for a rescue deal.
  • Thames Water on cusp of public ownership after ‘weak’ deal

    Water
    Thames Water creditors have made a last-ditch offer for a rescue deal.
  • Andy Burnham says he will put essential services back under ‘stronger’ public control

    Politics
    Andy Burnham discussing capital gains tax increase during a press conference, highlighting potential economic impacts
  • Exclusive: Reynolds never met Thames Water investors before rejecting rescue deal

    Water
    Emma Reynolds speaking at a business conference podium, engaging audience with insights on industry trends and strategies.
  • Public markets, not the state, can fix the water sector

    Opinion
    Ofwat penalties start to mount for the sector
  • Burnham’s new chief of staff ran City firm advising Thames Water and rival Heathrow bidder

    Advisory
    James Purnell of Flint Global, highlighted in a business setting last year, showcasing leadership in strategic consulting.

City PM — European politics, business and analysis.

Europe

  • Germany
  • France
  • Europe
  • UK & Ireland

Topics

  • Business
  • Markets
  • AI
  • Technology
  • Opinion
  • Energy

More

  • Politics
  • Economics
  • Fintech
  • Legal
  • Sport
  • Life

Company

  • About City PM
  • Editorial Policy
  • Corrections
  • Contact
  • Terms of Use
  • Privacy Policy
  • Cookie Policy
© 2026 City PM · Published by CityPM Media, Bahnhofstrasse 65, 8001 Zürich, Switzerland
About · Editorial Policy · Corrections · Contact · Privacy · Facebook