Tuesday 22 October 2019 3:21 pm  |  Updated:  Tuesday 22 October 2019 5:09 pm

Crossrail at risk of facing further delays

By: Stefan Boscia

Add as a preferred source on Google
Crossrail

Crossrail is increasingly likely to face further cost blowouts and delays, according to a new report.

The £15.9bn underground rail line was due to open in December 2018, but now has a target date of between October 2020 and March 2021.

Read more: Crossrail to renegotiate pay with Bechtel

However, a new report from Jacobs Engineering, who is responsible for oversight of project delivery, said the risks of missing this target range have increased.

Jacobs said the project is starting to miss key dates after a “relatively stable” past four quarters, partly due to lower-than-expected productivity.

The report said trials are still expected to begin in February next year, but the process may take longer than planned.

Crossrail

“Dates are now slipping, to various degrees, all of which has an impact on the opening date window,” the report read.

“The delivery dates by Crossrail are under increasing pressure each period and are less likely to be achieved.”

This, in turn, has created an increasing chance of cost blowouts.

Jacobs said: “The financial impact of not meeting these dates is not immediately picked up with the Anticipated Final Costs, as these can take a period to manifest in revised forecasts.”

Crossrail chief executive Mark Wild has said the projections for the “central cost forecast” are £42m more than the currently committed funding.

Read more

Upgrading the grid risks ending up like HS2

Electricity grid infrastructure with high-voltage power lines and pylons under a clear sky, representing energy distribution.

Wild sent a letter to London Assembly transport committee head Florence Eshalomi yesterday also outlining the risk of potential delays.

He said he still expected Crossrail to meet its target date, but that “this is the most difficult and challenging phase” of the project.

“Our cost forecasts show that the project’s costs could increase if all the identified risks and uncertainties were not mitigated,” he said.

“Additional modelling scenarios that we have carried out with a significantly higher level of risk contingency, currently show up to £392m could be required above the committed funding, with the Elizabeth line opening later in 2021.

“We continue to see positive performance against our schedule baseline and in the context of the various risks and opportunities, we still expect that the project can be delivered within the financing package agreed by our Sponsors in December 2018.”

However, Jacobs said the risks would be difficult to mitigate.

“The risks that have increased are not technical, but contractual, which are harder to mitigate,” the report read.

Read more: Crossrail contractors could ask for more money to meet opening deadlines

“Crossrail is planning to mitigate the delay, however the underpinning mitigation plans are still awaited.”

Crossrail will be known as the Elizabeth line when it opens and will span 73 miles, from Reading, Berkshire, to Shenfield, Essex.

Read more

Staff burnout soars in professional services due to inefficiencies and outdated IT

Businessman eating lunch outdoors in Canada financial district

Share this article

  • Facebook
  • X
  • LinkedIn
  • WhatsApp
  • Email

Similarly tagged content:

Sections

  • News

Categories

  • Transport & Infrastructure

Related Topics

  • Crossrail
  • London business

Trending Articles

  • Top Burnham adviser calls for capital gains and inheritance tax hikes

  • A meeting with the breakfast king of Mayfair

  • Clarkson’s Farm and why businesses must stop blaming the weather

  • FTSE 100 Live: Stocks jump on defence and metals boost; Oil on track to shed a fifth on US-Iran peace hopes

  • BT tops FTSE 100 after finding new home for international business with Verizon joint venture

More from City PM

  • Upgrading the grid risks ending up like HS2

    Opinion
    Electricity grid infrastructure with high-voltage power lines and pylons under a clear sky, representing energy distribution.
  • Staff burnout soars in professional services due to inefficiencies and outdated IT

    Prof Services
    Businessman eating lunch outdoors in Canada financial district
  • Kolibri Global Energy Inc. Provides Strategy Update and Higher 2026 Forecast

    Business Wire
  • EU airport chief: ‘I don’t know how we’ll cope’ with new border system

    Transport & Infrastructure
    Drop off charges at UK airports have reached the highest level on record amid booming travel demand this summer.
  • Defence and immigration help Serco weather outsourcing pressure

    Business
    Serco has benefitted from a Western increase in defence spending
  • BT boss bags pay rise despite £3.7bn cost-cutting drive

    Telecoms
    BT's first female boss Allison Kirkby has a strong CV but the telecoms veteran has a tough job ahead of her.
  • Let’s help London’s £53.5bn airport investment opportunity take off

    Opinion
    Commercial airplane flying in clear blue sky, representing aviation news and current trends in the airline industry.
  • Babcock predicts global government defence spending spree after hit to profit

    Investing
    Babcock is a member of the FTSE 100.

City PM — European politics, business and analysis.

Europe

  • Germany
  • France
  • Europe
  • UK & Ireland

Topics

  • Business
  • Markets
  • AI
  • Technology
  • Opinion
  • Energy

More

  • Politics
  • Economics
  • Fintech
  • Legal
  • Sport
  • Life

Company

  • About City PM
  • Editorial Policy
  • Corrections
  • Contact
  • Terms of Use
  • Privacy Policy
  • Cookie Policy
© 2026 City PM · Published by CityPM Media, Bahnhofstrasse 65, 8001 Zürich, Switzerland
About · Editorial Policy · Corrections · Contact · Privacy