Hinkley Point crisis deepens as experts warn that there’s “zero possibility” of the project being finished by 2025

By: Shruti Tripathi

Add as a preferred source on Google

The government is facing fresh calls to reconsider its plan to build two nuclear reactors at Hinkley Point in Somerset, with experts warning that there’s “zero possibility” of the controversial project being finished by 2025.

The concerns come after Vincent de Rivaz, the French utility giant’s UK boss, failed to assure parliament's energy and climate change committee yesterday that it will able to meet that deadline. He was hauled before MPs amid repeated delays to when EDF will make a final investment decision.

“At the moment of final investment decision (FID) we will confirm a date,” De Rivaz said in response to whether the nuclear power plant will be completed on time. The FID will be taken following a consultation with French unions.

Read more: Hollande renews support for EDF's Hinkley Point

The £21bn project, a cornerstone of the government’s energy policy, has been beset by concerns over its affordability for EDF and consequent opposition from the French unions. There are also question marks over the viability of the EPR nuclear reactors, brainchild of EDF’s engineering partner Areva.

“I think there’s zero possibility of it being completed by 2025,” said Jeremy Nicholson of the Energy Intensive Users Group. “There’s a theoretical possibility it could be completed by 2027, but I wouldn't wish to bet on it. I don't think the secretary of state should either… The most sensible thing would be to carry on discussions with EDF in case there are means by which the price and delivery rate can be managed, but to recognise that this is looking increasingly implausible. There’s no dishonour in working on plan B if plan A doesn't work.”

Asked whether the UK government should change course and abandon the deal with EDF, Peter Atherton, managing director and head of European utility sector research at Jefferies, said: “Yes, that would be a sensible piece of public policy. But the government shows no signs of doing that.”

Read more: EDF warns Hinkley costs could rise by nearly £3bn

Paul Dorfman, a senior research fellow at UCL’s Energy Institute, added: “This thing cannot be built on time, it’s a failed piece of kit. Even if it were to get an approval there’s no way of knowing when the UK could rely on any power from Hinkley.”

The alternatives include other nuclear technologies and gas-fired stations, but both bring their own challenges.

Andrea Leadsom, energy minister, said yesterday she remains “fully confident” that Hinkley will go ahead.

Share this article

  • Facebook
  • X
  • LinkedIn
  • WhatsApp
  • Email

Similarly tagged content:

Sections

  • Markets & Economics
  • News

Categories

  • Business
  • Economics
  • Politics

Trending Articles

  • Billionaire Easyjet founder in line for £800m payday from takeover

  • Burnham told to launch £100bn tax reform package

  • Construction sector cuts jobs again as house building slumps

  • Pension pressure to help swell UK debt to three times size of economy

  • FTSE 100 Live: Stocks slump as oil soars; Trump hits out at ‘cuckoo’ Iran

More from City PM

  • Babcock predicts global government defence spending spree after hit to profit

    Investing
    Babcock is a member of the FTSE 100.
  • Rolls-Royce shares surge as SMR unit bags multi-billion pound Swedish nuclear contract

    Energy
    Rendering of a small modular reactor (SMR) design showcasing compact and efficient nuclear energy solution
  • X-energy Submits Xe-100 HTGR for UK Generic Design Assessment

    Business Wire
  • Starmer scrambles to make savings in bid to boost defence spending

    Politics
    Keir Starmer discussing UKs defense strategy with BAE Systems executives in a formal meeting setting
  • Quaise Energy Raises $134 Million in Initial Close of Series B to Build World’s First Superhot Geothermal Power Plant

    Business Wire
  • Carbon markets must industrialise or the net zero transition stalls

    Partner
    Close-up of a sapling at Aranya Reforestation site in India, showcasing efforts in sustainable forestry and ecological res...
  • The world needs an answer on climate finance – it’s London

    Opinion
    Corporate philanthropy concept with diverse professionals collaborating on sustainable, long-term global health solutions
  • As it happened: Stocks recover after markets rocked by tech-sell off; US claims ‘good foundations’ of Iran deal

    Markets
    Breaking news illustration with abstract globe, digital connections, and stock market growth indicators on a business news...

City PM — European politics, business and analysis.

Europe

  • Germany
  • France
  • Europe
  • UK & Ireland

Topics

  • Business
  • Markets
  • AI
  • Technology
  • Opinion
  • Energy

More

  • Politics
  • Economics
  • Fintech
  • Legal
  • Sport
  • Life

Company

  • About City PM
  • Editorial Policy
  • Corrections
  • Contact
  • Terms of Use
  • Privacy Policy
  • Cookie Policy
© 2026 City PM · Published by CityPM Media, Bahnhofstrasse 65, 8001 Zürich, Switzerland
About · Editorial Policy · Corrections · Contact · Privacy